... 46. To ensure that the information gathered through the registration is kept up-to-date, an obligation on registrants to inform the Agency of certain changes to the information should be introduced. ...
... 60. For enforcement and evaluation purposes, downstream users of substances should be required to report to the Agency certain basic information if their use is outside the conditions of the exposure scenario detailed in the safety data sheet communicated by their original manufacturer or importer and to keep such reported information up-to-date. ...


ARTICLE-8: Only representative of a non-Community manufacturer     [go to this ARTICLE]
... 2. The representative shall also comply with all other obligations of importers under this Regulation. To this end, he shall have a sufficient background in the practical handling of substances and the information related to them and, without prejudice to Article 36, shall keep available and up-to-date information on quantities imported and customers sold to, as well as information on the supply of the latest update of the safety data sheet referred to in Article 31. ...


ARTICLE-9: Exemption from the general obligation to register for product and process orientated research and development (PPORD)     [go to this ARTICLE]
... 3. The Agency shall check the completeness of the information supplied by the notifier and Article 20(2) shall apply adapted as necessary. The Agency shall assign a number to the notification and a notification date, which shall be the date of receipt of the notification at the Agency, and shall forthwith communicate that number and date to the manufacturer, or importer, or producer of articles concerned. The Agency shall also communicate this information to the competent authority of the Member State(s) concerned. ...
... 3. The Agency shall check the completeness of the information supplied by the notifier and Article 20(2) shall apply adapted as necessary. The Agency shall assign a number to the notification and a notification date, which shall be the date of receipt of the notification at the Agency, and shall forthwith communicate that number and date to the manufacturer, or importer, or producer of articles concerned. The Agency shall also communicate this information to the competent authority of the Member State(s) concerned. ...
... 3. The Agency shall check the completeness of the information supplied by the notifier and Article 20(2) shall apply adapted as necessary. The Agency shall assign a number to the notification and a notification date, which shall be the date of receipt of the notification at the Agency, and shall forthwith communicate that number and date to the manufacturer, or importer, or producer of articles concerned. The Agency shall also communicate this information to the competent authority of the Member State(s) concerned. ...


ARTICLE-14: Chemical safety report and duty to apply and recommend risk reduction measures     [go to this ARTICLE]
... 7. Any registrant required to conduct a chemical safety assessment shall keep his chemical safety report available and up to date. ...


ARTICLE-15: Substances in plant protection and biocidal products     [go to this ARTICLE]
... 2. Active substances manufactured or imported for use in biocidal products only and included either in Annexes I, IA or IB to Directive 98/8/EC of the European Parliament and of the Council of 16 February 1998 concerning the placing of biocidal products on the market(6)or in Commission Regulation (EC) No 2032/2003 of 4 November 2003 on the second phase of the 10-year work programme referred to in Article 16(2) of Directive 98/8/EC(7), until the date of the decision referred to in the second subparagraph of Article 16(2) of Directive 98/8/EC, shall be regarded as being registered and the registration as completed for manufacture or import for the use in a biocidal product and therefore as fulfilling the requirements of Chapters 1 and 5 of this Title. ...


ARTICLE-20: Duties of the Agency     [go to this ARTICLE]
... 1. The Agency shall assign a submission number to each registration, which is to be used for all correspondence regarding the registration until the registration is deemed to be complete, and a submission date, which shall be the date of receipt of the registration at the Agency. ...
... 1. The Agency shall assign a submission number to each registration, which is to be used for all correspondence regarding the registration until the registration is deemed to be complete, and a submission date, which shall be the date of receipt of the registration at the Agency. ...
... 2. The Agency shall undertake a completeness check of each registration in order to ascertain that all the elements required under Articles 10 and 12 or under Articles 17 or 18, as well as the registration fee referred to in Article 6(4), Article 7(1) and (5), Article 17(2) or Article 18(2), have been provided. The completeness check shall not include an assessment of the quality or the adequacy of any data or justifications submitted. The Agency shall undertake the completeness check within three weeks of the submission date, or within three months of the relevant deadline of Article 23, as regards registrations of phase-in substances submitted in the course of the two-month period immediately preceding that deadline. If a registration is incomplete, the Agency shall inform the registrant, before expiry of the three-week or three-month period referred to in the second subparagraph, as to what further information is required in order for the registration to be complete, while setting a reasonable deadline for this. The registrant shall complete his registration and submit it to the Agency within the deadline set. The Agency shall confirm the submission date of the further information to the registrant. The Agency shall perform a further completeness check, considering the further information submitted. The Agency shall reject the registration if the registrant fails to complete his registration within the deadline set. The registration fee shall not be reimbursed in such cases. ...
... 2. The Agency shall undertake a completeness check of each registration in order to ascertain that all the elements required under Articles 10 and 12 or under Articles 17 or 18, as well as the registration fee referred to in Article 6(4), Article 7(1) and (5), Article 17(2) or Article 18(2), have been provided. The completeness check shall not include an assessment of the quality or the adequacy of any data or justifications submitted. The Agency shall undertake the completeness check within three weeks of the submission date, or within three months of the relevant deadline of Article 23, as regards registrations of phase-in substances submitted in the course of the two-month period immediately preceding that deadline. If a registration is incomplete, the Agency shall inform the registrant, before expiry of the three-week or three-month period referred to in the second subparagraph, as to what further information is required in order for the registration to be complete, while setting a reasonable deadline for this. The registrant shall complete his registration and submit it to the Agency within the deadline set. The Agency shall confirm the submission date of the further information to the registrant. The Agency shall perform a further completeness check, considering the further information submitted. The Agency shall reject the registration if the registrant fails to complete his registration within the deadline set. The registration fee shall not be reimbursed in such cases. ...
... 3. Once the registration is complete, the Agency shall assign a registration number to the substance concerned and a registration date, which shall be the same as the submission date. The Agency shall without delay communicate the registration number and registration date to the registrant concerned. The registration number shall be used for all subsequent correspondence regarding registration. ...
... 3. Once the registration is complete, the Agency shall assign a registration number to the substance concerned and a registration date, which shall be the same as the submission date. The Agency shall without delay communicate the registration number and registration date to the registrant concerned. The registration number shall be used for all subsequent correspondence regarding registration. ...
... 3. Once the registration is complete, the Agency shall assign a registration number to the substance concerned and a registration date, which shall be the same as the submission date. The Agency shall without delay communicate the registration number and registration date to the registrant concerned. The registration number shall be used for all subsequent correspondence regarding registration. ...
... 4. The Agency shall notify the competent authority of the relevant Member State within 30 days of the submission date, that the following information is available in the Agency database: ...
... (b) the submission or registration date; ...


ARTICLE-21: Manufacturing and import of substances     [go to this ARTICLE]
... 1. A registrant may start or continue the manufacture or import of a substance or production or import of an article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the submission date, without prejudice to Article 27(8). In the case of registrations of phase-in substances, such a registrant may continue the manufacture or import of the substance or production or import of an article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the submission date or, if submitted within the two-month period before the relevant deadline of Article 23, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three months from that deadline, without prejudice to Article 27(8). In the case of an update of a registration according to Article 22 a registrant may continue the manufacture or import of the substance, or the production or import of the article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the update date, without prejudice to Article 27(8). ...
... 1. A registrant may start or continue the manufacture or import of a substance or production or import of an article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the submission date, without prejudice to Article 27(8). In the case of registrations of phase-in substances, such a registrant may continue the manufacture or import of the substance or production or import of an article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the submission date or, if submitted within the two-month period before the relevant deadline of Article 23, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three months from that deadline, without prejudice to Article 27(8). In the case of an update of a registration according to Article 22 a registrant may continue the manufacture or import of the substance, or the production or import of the article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the update date, without prejudice to Article 27(8). ...
... 1. A registrant may start or continue the manufacture or import of a substance or production or import of an article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the submission date, without prejudice to Article 27(8). In the case of registrations of phase-in substances, such a registrant may continue the manufacture or import of the substance or production or import of an article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the submission date or, if submitted within the two-month period before the relevant deadline of Article 23, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three months from that deadline, without prejudice to Article 27(8). In the case of an update of a registration according to Article 22 a registrant may continue the manufacture or import of the substance, or the production or import of the article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the update date, without prejudice to Article 27(8). ...


ARTICLE-30: Sharing of data involving tests     [go to this ARTICLE]
... 3. If the owner of a study as referred to in paragraph 1 which involves testing on vertebrate animals refuses to provide either proof of the cost of that study or the study itself to (an)other participant(s), he shall not be able to proceed with registration until he provides the information to the other participants(s). The other participant(s) shall proceed with registration without fulfilling the relevant information requirement, explaining the reason for this in the registration dossier. The study shall not be repeated unless within 12 months of the date of registration of the other participant(s), the owner of this information has not provided it to them and the Agency decides that the test should be repeated by them. However, if a registration containing this information has already been submitted by another registrant, the Agency shall give the other participant(s) permission to refer to the information in his registration dossier(s). The other registrant shall have a claim on the other participant(s) for an equal share of the cost, provided he makes the full study report available to the other participant(s), which shall be enforceable in the national courts. ...


ARTICLE-31: Requirements for Safety Data Sheets     [go to this ARTICLE]
... The new, dated version of the information, identified as "Revision: (date)", shall be provided free of charge on paper or electronically to all former recipients to whom they have supplied the substance or preparation within the preceding 12 months. Any updates following registration shall include the registration number. ...


ARTICLE-37: Downstream user chemical safety assessments and duty to identify, apply and recommend risk reduction measures     [go to this ARTICLE]
... 7. Downstream users shall keep their chemical safety report up to date and available. ...


ARTICLE-40: Examination of testing proposals     [go to this ARTICLE]
... 2. Information relating to testing proposals involving tests on vertebrate animals shall be published on the Agency website. The Agency shall publish on its website the name of the substance, the hazard end-point for which vertebrate testing is proposed, and the date by which any third party information is required. It shall invite third parties to submit, using the format provided by the Agency, scientifically valid information and studies that address the relevant substance and hazard end-point, addressed by the testing proposal, within 45 days of the date of publication. All such scientifically valid information and studies received shall be taken into account by the Agency in preparing its decision in accordance with paragraph 3. ...
... 2. Information relating to testing proposals involving tests on vertebrate animals shall be published on the Agency website. The Agency shall publish on its website the name of the substance, the hazard end-point for which vertebrate testing is proposed, and the date by which any third party information is required. It shall invite third parties to submit, using the format provided by the Agency, scientifically valid information and studies that address the relevant substance and hazard end-point, addressed by the testing proposal, within 45 days of the date of publication. All such scientifically valid information and studies received shall be taken into account by the Agency in preparing its decision in accordance with paragraph 3. ...


ARTICLE-56: General provisions     [go to this ARTICLE]
... (c) the date referred to in Article 58(1)(c)(i) has not been reached; or ...
... (d) the date referred to in Article 58(1)(c)(i) has been reached and he made an application 18 months before that date but a decision on the application for authorisation has not yet been taken; or ...
... (d) the date referred to in Article 58(1)(c)(i) has been reached and he made an application 18 months before that date but a decision on the application for authorisation has not yet been taken; or ...


ARTICLE-58: Inclusion of substances in Annex XIV     [go to this ARTICLE]
... (i) the date(s) from which the placing on the market and the use of the substance shall be prohibited unless an authorisation is granted (hereinafter referred to as "the sunset date") which should take into account, where appropriate, the production cycle specified for that use; ...
... (i) the date(s) from which the placing on the market and the use of the substance shall be prohibited unless an authorisation is granted (hereinafter referred to as "the sunset date") which should take into account, where appropriate, the production cycle specified for that use; ...
... (ii) a date or dates at least 18 months before the sunset date(s) by which applications must be received if the applicant wishes to continue to use the substance or place it on the market for certain uses after the sunset date(s); these continued uses shall be allowed after the sunset date until a decision on the application for authorisation is taken; ...
... (ii) a date or dates at least 18 months before the sunset date(s) by which applications must be received if the applicant wishes to continue to use the substance or place it on the market for certain uses after the sunset date(s); these continued uses shall be allowed after the sunset date until a decision on the application for authorisation is taken; ...
... (ii) a date or dates at least 18 months before the sunset date(s) by which applications must be received if the applicant wishes to continue to use the substance or place it on the market for certain uses after the sunset date(s); these continued uses shall be allowed after the sunset date until a decision on the application for authorisation is taken; ...
... (ii) a date or dates at least 18 months before the sunset date(s) by which applications must be received if the applicant wishes to continue to use the substance or place it on the market for certain uses after the sunset date(s); these continued uses shall be allowed after the sunset date until a decision on the application for authorisation is taken; ...
... 4. Before the Agency sends its recommendation to the Commission it shall make it publicly available on its website, clearly indicating the date of publication, taking into account Articles 118 and 119 on access to information. The Agency shall invite all interested parties to submit comments within three months of the date of publication, in particular on uses which should be exempt from the authorisation requirement. The Agency shall update its recommendation, taking into account the comments received. ...
... 4. Before the Agency sends its recommendation to the Commission it shall make it publicly available on its website, clearly indicating the date of publication, taking into account Articles 118 and 119 on access to information. The Agency shall invite all interested parties to submit comments within three months of the date of publication, in particular on uses which should be exempt from the authorisation requirement. The Agency shall update its recommendation, taking into account the comments received. ...


ARTICLE-64: Procedure for authorisation decisions     [go to this ARTICLE]
... 1. The Agency shall acknowledge the date of receipt of the application. The Agency's Committees for Risk Assessment and Socio-economic Analysis shall give their draft opinions within ten months of the date of receipt of the application. ...
... 1. The Agency shall acknowledge the date of receipt of the application. The Agency's Committees for Risk Assessment and Socio-economic Analysis shall give their draft opinions within ten months of the date of receipt of the application. ...
... 9. Summaries of the Commission decisions, including the authorisation number and the reasons for the decision, in particular where suitable alternatives exist, shall be published in the Official Journal of the European Union and shall be made publicly available in a database established and kept up to date by the Agency. ...


ARTICLE-66: Downstream users     [go to this ARTICLE]
... 2. The Agency shall establish and keep up to date a register of downstream users who have made a notification in accordance with paragraph 1. The Agency shall grant access to this register to the competent authorities of the Member States. ...


ARTICLE-69: Preparation of a proposal     [go to this ARTICLE]
... 2. After the date referred to in Article 58(1)(c)(i) for a substance listed in Annex XIV, the Agency shall consider whether the use of that substance in articles poses a risk to human health or the environment that is not adequately controlled. If the Agency considers that the risk is not adequately controlled, it shall prepare a dossier which conforms to the requirements of Annex XV. ...
... 4. If a Member State considers that the manufacture, placing on the market or use of a substance on its own, in a preparation or in an article poses a risk to human health or the environment that is not adequately controlled and needs to be addressed it shall notify the Agency that it proposes to prepare a dossier which conforms to the requirements of the relevant sections of Annex XV. If the substance is not on the list maintained by the Agency referred to in paragraph 5 of this Article, the Member State shall prepare a dossier which conforms to the requirements of Annex XV within 12 months of the notification to the Agency. If this dossier demonstrates that action on a Community-wide basis is necessary, beyond any measures already in place, the Member State shall submit it to the Agency in the format outlined in Annex XV, in order to initiate the restrictions process. The Agency or Member States shall refer to any dossier, chemical safety report or risk assessment submitted to the Agency or Member State under this Regulation. The Agency or Member States shall also refer to any relevant risk assessment submitted for the purposes of other Community Regulations or Directives. To this end other bodies, such as agencies, established under Community law and carrying out a similar task shall provide information to the Agency or Member State concerned on request. The Committee for Risk Assessment and the Committee for Socio-economic Analysis shall check whether the dossier submitted conforms to the requirements of Annex XV. Within 30 days of receipt, the respective Committee shall inform the Agency or the Member State suggesting restrictions, as to whether the dossier conforms. If the dossier does not conform, the reasons shall be given to the Agency or the Member State in writing within 45 days of receipt. The Agency or the Member State shall bring the dossier into conformity within 60 days of the date of receipt of the reasons from the Committees, otherwise the procedure under this Chapter shall be terminated. The Agency shall publish without delay the intention of the Commission or of a Member State to instigate a restriction procedure for a substance and shall inform those who submitted a registration for that substance. ...
... 6. Without prejudice to Articles 118 and 119, the Agency shall make publicly available on its website all dossiers conforming with Annex XV including the restrictions suggested pursuant to paragraphs 3 and 4 of this Article without delay, clearly indicating the date of publication. The Agency shall invite all interested parties to submit individually or jointly within 6 months of the date of publication: ...
... 6. Without prejudice to Articles 118 and 119, the Agency shall make publicly available on its website all dossiers conforming with Annex XV including the restrictions suggested pursuant to paragraphs 3 and 4 of this Article without delay, clearly indicating the date of publication. The Agency shall invite all interested parties to submit individually or jointly within 6 months of the date of publication: ...


ARTICLE-70: Agency opinion: Committee for Risk Assessment     [go to this ARTICLE]
... Within nine months of the date of publication referred to in Article 69(6), the Committee for Risk Assessment shall formulate an opinion as to whether the suggested restrictions are appropriate in reducing the risk to human health and/or the environment, based on its consideration of the relevant parts of the dossier. This opinion shall take account of the Member State dossier or of the dossier prepared by the Agency at the request of the Commission, and the views of interested parties referred to in point (a) of Article 69(6). ...


ARTICLE-71: Agency opinion: Committee for Socio-economic Analysis     [go to this ARTICLE]
... 1. Within 12 months of the date of publication referred to in Article 69(6), the Committee for Socio-economic Analysis shall formulate an opinion on the suggested restrictions, based on its consideration of the relevant parts of the dossier and the socio-economic impact. It shall prepare a draft opinion on the suggested restrictions and on the related socio-economic impact, taking account of the analyses or information according to point (b) of Article 69(6), if there are any. The Agency shall publish the draft opinion on its website without delay. The Agency shall invite interested parties to give their comments on the draft opinion no later than 60 days from the publication of that draft opinion. ...


ARTICLE-87: Rapporteurs of Committees and use of experts     [go to this ARTICLE]
... 2. Member States shall transmit to the Agency the names of experts with proven experience in the tasks required by Article 77, who would be available to serve on working groups of the Committees, together with an indication of their qualifications and specific areas of expertise. The Agency shall keep an up-to-date list of experts. The list shall include the experts referred to in the first subparagraph and other experts identified directly by the Secretariat. ...


ARTICLE-96: The budget of the Agency     [go to this ARTICLE]
... 11. The Management Board shall, without delay, notify the budgetary authority of its intention to implement any project which may have significant financial implications for the funding of its budget, in particular any projects relating to property such as the rental or purchase of buildings. It shall inform the Commission thereof. Where a branch of the budgetary authority has notified its intention to deliver an opinion, it shall forward its opinion to the Management Board within a period of six weeks from the date of notification of the project. ...


ARTICLE-129: Safeguard clause     [go to this ARTICLE]
... 3. If, in the case of a decision as referred to in point (a) of paragraph 2, the provisional measure taken by the Member State consists in a restriction on the placing on the market or use of a substance, the Member State concerned shall initiate a Community restrictions procedure by submitting to the Agency a dossier, in accordance with Annex XV, within three months of the date of the Commission decision. ...